The 900t gantry crane is key equipment for beam prefabrication plants in railway passenger dedicated lines, primarily used for lifting, transporting, and loading 20m, 24m, and 32m double-track full-span box girders. This design addresses the specific requirements of precast beam construction, integrating advanced crane technology from domestic and international sources to propose a complete solution for the hoisting mechanism.
Based on the application scenario, the 900t gantry crane can be categorized into two types: double-gantry structure and single-main-girder structure. The double-gantry structure facilitates longitudinal passage of beam transport vehicles without being constrained by their length during loading; whereas the single-main-girder structure utilizes a rigid leg and a flexible leg for support, featuring a compact design. This design references the MGHZ900t beam handler, which has a rated lifting capacity of 900t (excluding spreader self-weight), a total machine weight of 480t, an inner clear span of 40m, and a lifting height of 9.8m.
As the core system of the gantry crane, the hoisting mechanism mainly consists of the following key components:
During operation, the motor drives the reducer via the coupling, the output shaft of the reducer drives the drum to rotate, and the lifting and lowering motion of the spreader is achieved through the wire rope and pulley block. The entire system employs closed-loop control, enabling positioning accuracy within millimeters.
Motor power P can be calculated based on the hoisting weight, hoisting speed, and mechanism efficiency:
P = (Q × v) / (6120 × η)
Where:
Calculating with a hoisting speed of 0.8 m/min:
P = (950 × 1000 × 0.8) / (6120 × 0.85) ≈ 146 kW
Considering starting inertia and other factors, a 2 × 160 kW motor set is actually selected.
The breaking force S of the wire rope shall satisfy:
S ≥ n × S_max
Where:
Based on the pulley block multiplicity m=12, the tension in a single wire rope is:
S_max = (950 × 1000 × 9.8) / (2 × 12 × 1000) ≈ 388 kN
Therefore, the wire rope breaking force S ≥ 6 × 388 = 2328 kN
Select a 40mm diameter wire rope with a nominal tensile strength of 1870 MPa and an independent wire rope core.
Drum diameter D ≥ 20d = 20 × 40 = 800 mm, take D = 1000 mm
The drum length L depends on the wire rope working length and the number of winding layers. For a lifting height H=9.8m and pulley block multiplicity m=12:
Wire rope working length = m × H = 12 × 9.8 = 117.6 m
Considering safety wraps, etc., the total rope length is about 130 m.
Using a twin drum, the rope capacity per side is 65 m, wound in 2 layers:
L = 65 / (π × 1.0 × 2) ≈ 10.34 m
Take L = 11 m.
Total transmission ratio i of the hoisting mechanism:
i = (n_m × π × D) / (v × m)
Where:
i = (1500 × π × 1.0) / (0.8 × 12) ≈ 490
Select a two-stage planetary gear reducer with a transmission ratio of 500:1.
The main girder of the 900t gantry crane can adopt a double-main-girder or single-main-girder structure. Referencing the MGHZ900t beam handler, when using a single-main-girder design, the following must be met:
Main girder cross-section dimensions are determined based on load calculations:
A combination of rigid leg and flexible leg design is adopted:
The leg cross-section is typically designed as a box structure with high bending and torsional stiffness. Based on the experience of the MDGE900t beam handler, the leg height must accommodate the required lifting height of 9.8m.
Finite element software like ABAQUS is used to establish a detailed 3D model of the main girder, analyzing stress distribution and deformation under different load combinations. Main analysis conditions include:
The analysis results are used to optimize the main girder cross-section dimensions and stiffener layout, ensuring the maximum stress does not exceed the allowable value and deformation meets usage requirements.
The main functions of the hoisting mechanism’s hydraulic system include:
The hydraulic system uses load-sensing variable pumps and proportional valves to match flow and pressure with the load, improving energy efficiency.
The control system adopts a PLC + frequency converter scheme to achieve the following functions:
Referencing the overall lifting construction method for the 900-ton gantry crane, the control system can achieve computer remote control and full-process program control with live monitoring.
The hoisting mechanism of the 900t gantry crane must be equipped with comprehensive safety protection devices:
Referencing the overall lifting construction method for the 900-ton gantry crane, attention during installation is needed for:
To ensure long-term reliable operation of the 900t gantry crane hoisting mechanism, a regular maintenance system should be established:
Pay special attention to wire rope maintenance, regularly checking for broken wires, wear, and corrosion. The rope must be replaced immediately when the number of broken wires reaches the discard criteria.
This hoisting mechanism design for the 900t gantry crane features the following innovations:
This design scheme proposes a complete solution for the hoisting mechanism of the 900t gantry crane, specifically addressing the requirements of railway passenger dedicated line precast beam construction. Through precise parameter calculation, finite element structural analysis, and advanced control system design, the safety, reliability, and advancement of the hoisting mechanism are ensured. This design incorporates mature experience from domestic and international crane design and introduces several innovations, enabling it to meet the high standards required for large-scale lifting equipment in modern beam prefabrication plants.
In practical application, it is recommended to further optimize details based on specific construction conditions and strictly adhere to relevant standards for manufacturing, installation, and acceptance to ensure the equipment performance meets design expectations.
Contact our crane specialists
Send us a message and we will get back to you as soon as possible.