HomeGantry crane → Double-Girder Gantry Crane Trolley Design Scheme

Double-Girder Gantry Crane Trolley Design Scheme

This design scheme provides a systematic design for the double-girder gantry crane trolley, comprehensively considering the current research status domestically and internationally, structural design, mechanism calculation, safety standards, and practical application requirements. The double-girder gantry crane serves as essential loading and unloading equipment in modern industrial and mining enterprises, railway stations, ports, and construction sites. The trolley design directly impacts the performance and reliability of the entire machine. The following sections provide a detailed elaboration from the aspects of design key points, structural analysis, mechanism calculation, material selection, and safety specifications.

Design Overview and General Requirements

The double-girder gantry crane trolley is the core component of the entire machine, primarily responsible for the vertical hoisting and horizontal movement of goods. According to industry trends and current research, modern crane design is developing towards high efficiency, intelligence, and modularity. This design is based on typical parameters of 150-ton capacity and 20-meter span, adopting a modular design concept to improve the commonality of standard parts, facilitating production organization and maintenance.

Basic Design Parameters:

  • Rated Lifting Capacity: Main hook 150 tons (can be designed with main and auxiliary dual trolley structure, such as 2×100 ton tandem lift for 200 ton capacity)
  • Span: 20 meters
  • Duty Class: A5 (Medium duty)
  • Lifting Height: Main hook 12 meters (adjustable according to user requirements)
  • Trolley Travel Speed: 20-30 m/min (Variable Frequency Drive speed control)
  • Hoisting Speed: Main hook 1.5-2 m/min (low speed under heavy load), Auxiliary hook (if equipped) 8-10 m/min
Double-Girder Gantry Crane Trolley

The trolley design must meet three typical working condition requirements: single trolley under full load, dual trolleys in tandem lift (if using a dual trolley structure), and stability requirements under dynamic loads. Especially under the dual trolley tandem lift condition, it is necessary to ensure synchronous operation of the two trolleys and even load distribution to avoid additional torque on the main girder.

The design process follows a “calculation-design-verification” cycle. First, basic parameters are determined based on usage requirements, then mechanism layout and component selection are performed, and finally, strength, stiffness, stability, and other aspects are verified to ensure design rationality. It is worth noting that to simplify the production process, some designs can directly adopt the structure of universal 5t-50t overhead crane trolleys, but large tonnage (e.g., 150 tons) requires customized design.

Trolley Structure Design

The structural design of the double-girder gantry crane trolley needs to comprehensively consider load-bearing capacity, travel stability, maintenance convenience, and appearance coordination. The trolley structure mainly consists of the frame, hoisting mechanism, travel mechanism, and safety protection devices. The overall layout must be compact and reasonable, ensuring no interference in the movement of various mechanisms.

Frame Design:

The frame serves as the skeleton of the trolley, bearing all loads and transferring them to the main girder. This design uses a welded steel box-section structure, characterized by high stiffness and strength. The frame is arranged with two load-bearing beams transversely, connected at both ends through end beams to form an integral frame structure. The height of the load-bearing beams is determined to be 800-1000mm based on the span and lifting capacity, with web thickness not less than 20mm (for 150-ton class), and top/bottom flange thickness of 25-30mm. To improve local stability, transverse stiffeners are installed inside the box beam every 1.5 meters, with additional reinforcement ribs added at the pulley block support locations.

The frame is connected to the main girder through wheel assemblies, using QU70 steel rail as the trolley travel rail. The wheel diameter is selected based on wheel pressure calculation. Typically, for a 150-ton class trolley, the wheel diameter is not less than 630mm, forged from 42CrMo alloy steel, with surface hardness reaching HB300-380 after quenched and tempered heat treatment. Wheel bearings are selected as double-row spherical roller bearings, which can automatically compensate for skewing caused by frame deformation.

Special Design for Dual Trolleys:

When using a main and auxiliary dual trolley configuration (e.g., 100t+100t=200t tandem lift), special attention must be paid to coordinated control and load distribution between the two trolleys. The two trolleys should maintain synchronous operation, with the spacing determined based on the size of the lifted object, typically not less than 1/3 of the span. Calculations show that when the dual trolleys are at the mid-span position, the main girder bending moment reaches its maximum, requiring reinforced frame design at this time. The dual trolley structure also requires mechanical and electrical interlocking devices to prevent single trolley overload.

Protection and Attachments:

The distance from the trolley canopy to the conductor bar is designed as 0.97 meters, and the distance to the railing is also maintained at 0.97 meters, ensuring maintenance space and electrical safety. The distance from the flange to the top plate of the main girder is 1.8 meters, facilitating installation and maintenance. Removable guardrails are installed on both sides of the trolley, with a height not less than 1 meter, and toe boards at the bottom to prevent tools from falling. The canopy is made of corrugated steel plate, which is both aesthetically pleasing and enhances local stiffness.

Hoisting Mechanism Design

The hoisting mechanism is the core component of the crane trolley, directly related to the safety and work efficiency of the entire machine. For the 150-ton class double-girder gantry crane, the hoisting mechanism needs to meet the working requirements of low speed under heavy load and high speed under light load, ensuring operational efficiency under different conditions.

Drive System Layout:

A parallel shaft arrangement is adopted. The motor is connected to the reducer via a highly flexible coupling, and the reducer output shaft drives the drum rotation through a gear coupling. This layout is compact, has high transmission efficiency, and is easy to maintain. The motor is selected from the YZP series metallurgical crane dedicated variable frequency motor, with insulation class F and protection class IP54. The power is determined based on the lifting capacity and speed calculation (150 tons approximately requires 2×75kW dual motor drive). The reducer is selected as the QJS type medium-hardened gear reducer. The speed ratio is determined based on the hoisting speed calculation. The input and output shafts are arranged in parallel, facilitating connection with the motor and drum.

Drum and Pulley Block:

The drum is made of 16Mn steel plate, rolled and welded. The diameter is determined based on the wire rope diameter (typically 20-25 times the wire rope diameter). The length must accommodate the entire wire rope winding neatly and leave not less than 3 dead wraps. Spiral grooves are provided at both ends of the drum to guide the orderly arrangement of the wire rope. The pulley block is made of cast steel structure. The pulley diameter is not less than 25 times the wire rope diameter. Bearings are selected as double-row spherical roller bearings to reduce friction resistance.

Wire Rope Selection:

Determined according to the GB/T3811-2008 standard calculation, for a 150-ton lifting capacity, multiple wire ropes are typically used to share the load. Select non-rotating multi-strand wire ropes with a tensile strength grade above 1870MPa, such as 36×K7 structure, with a single rope diameter not less than 28mm. The wire rope ends are fixed on the drum via clamps, with each rope tensioned independently to ensure even force distribution.

Braking System:

A two-stage braking system is installed for safety: primary braking is the hydraulic thruster brake integral to the motor; secondary braking is a disc brake installed on the reducer input shaft. The dual braking system ensures the load can be safely stopped even if any single brake fails. The braking torque of the brake is not less than 1.5 times the rated torque. During the static load test, the braking slippage should not exceed 1/100 of the drum rotation amount.

Hook Assembly:

The main hook uses a 150-ton class forged hook, made of DG20Mn material, with a trapezoidal cross-section for high strength and light weight. The hook is connected to the crossbeam via thrust bearings, allowing free rotation to prevent wire rope twisting. The hook assembly is equipped with safety attachments such as anti-roping devices and pulley guards.

Travel Mechanism Design

The design of the trolley travel mechanism must ensure that the crane trolley can move smoothly and accurately along the main girder rails, without creeping, slipping, or skewing. Considering the large tonnage characteristics of the double-girder gantry crane, the travel mechanism typically adopts a centralized drive or independent drive method.

Drive Method Selection:

For the 150-ton class trolley, independent drive is recommended, where the driving wheels on each side are driven by an independent drive unit. This method offers high transmission efficiency, flexible layout, and can effectively compensate for wheel skew caused by frame deformation. Each drive unit includes a motor, brake, reducer, and wheel assembly, connected by universal couplings to compensate for installation errors.

Motor and Reducer Selection:

The travel motor is selected from the YZR series wound rotor asynchronous motor. The power is determined based on the travel resistance calculation (150-ton class approximately requires 2×11kW). The reducer is selected as the QJ type crane dedicated reducer. The speed ratio is determined based on the required travel speed. The brake is selected as a hydraulic thruster brake, installed on the reducer input shaft, ensuring safe and reliable braking.

Wheels and Rails:

The wheel diameter is selected based on wheel pressure calculation. Typically, for a 150-ton class trolley, the wheel diameter is not less than 630mm. The wheel material is 42CrMo alloy steel, with tread surface quenched to hardness HB320-380, and depth not less than 15mm. The rail is selected as QU70 type, with hardness slightly lower than the wheels to reduce contact fatigue. Wheel bearings are selected as double-row tapered roller bearings, capable of withstanding large radial and axial loads.

Anti-Skew Measures:

Large-span trolley travel is prone to skew. The following measures are taken in the design: (1) Install horizontal guide wheels to maintain a constant gap between the trolley and the rail; (2) Use variable frequency speed control to ensure synchronous operation of motors on both sides; (3) Design the frame with sufficient stiffness to reduce skew caused by deformation.

Anti-Collision Protection:

Buffers (polyurethane or hydraulic buffers) are installed at both ends of the trolley to absorb impact energy. Limit switches and anti-collision devices are also installed to automatically decelerate and stop when approaching the end of the rail.

Table: Main Parameters for 150-ton Double-Girder Gantry Crane Trolley Travel Mechanism

Parameter NameValueRemarks
Drive MethodIndependent DriveIndependent drive on each side
Motor Power2×11kWYZR series
Reducer ModelQJ560Crane dedicated
Wheel DiameterΦ630mm42CrMo material
Rail ModelQU70High-strength crane rail
Travel Speed20-30 m/minVariable Frequency Drive control

Electrical Control System Design

The electrical control system for the modern double-girder gantry crane trolley has evolved from traditional relay control to an intelligent control system based on PLC + frequency converters, greatly improving travel smoothness, positioning accuracy, and energy efficiency.

Control Architecture:

The system adopts a distributed control architecture, consisting of the main PLC, frequency converters, sensors, and operator interfaces. The PLC serves as the control core, processing various input signals and outputting control commands; frequency converters drive the motors of each mechanism, enabling stepless speed control; sensors monitor the operating status of each mechanism in real time; operator interfaces include both cabin control and ground remote control.

Variable Frequency Speed Control Technology:

The hoisting mechanism uses vector control frequency converters to achieve constant torque control, ensuring high torque output at low speeds and precise stopping at high speeds. The travel mechanism uses VF control frequency converters,配合 braking units, to achieve smooth starting, braking, and speed regulation. The selection of frequency converters must consider the crane’s duty cycle, typically chosen as heavy-duty type, with a capacity one or two grades higher than the motor’s rated power.

Synchronous Control (Dual Trolleys):

When using a dual trolley structure, the two sets of hoisting and travel mechanisms must be strictly synchronized. The control system uses encoders to detect the position and speed difference of the two trolleys in real-time. The PLC performs PID calculations and adjusts the frequency converter output to ensure synchronization accuracy within 10mm. Load balancing detection is also set up; when the load difference between the two hooks exceeds 10% of the rated value, an alarm is triggered and unbalanced operation is stopped.

Safety Protection System:

Multiple safety protections are implemented: (1) Overload limiter, which cuts off hoisting power when the load exceeds 105% of the rated capacity; (2) Height limiters, preventing hook overwind; (3) Travel limiters, restricting the trolley’s travel range; (4) Emergency stop buttons, quickly cutting off power in dangerous situations. All safety devices are in independent circuits, directly cutting off the power supply without going through the PLC.

Monitoring and Diagnostics:

The system is equipped with a touch screen display, showing real-time parameters such as load, height, and travel position, and recording operational data and fault information. It has self-diagnostic functions to identify abnormal states like overload, overspeed, and motor overheating, providing handling suggestions.

Strength Calculation and Finite Element Analysis

As a key load-bearing component, the double-girder gantry crane trolley must undergo detailed strength, stiffness, and stability calculations to ensure it meets safety requirements under various working conditions. Modern design methods have evolved from traditional manual calculations to a combination of computer-aided design and finite element analysis.

Load Combination Analysis:

According to GB/T3811-2008 “Design Rules for Cranes”, the trolley structure needs to be calculated for the following three load combinations:

  1. Regular Load Combination: Includes dead weight, rated hoisting load, inertial loads, and other normal working loads.
  2. Occasional Load Combination: Adds occasional loads, such as skew travel lateral forces, collision forces, etc., to the regular loads.
  3. Special Load Combination: Considers special circumstances like non-working wind loads, seismic loads, etc.

Key Part Calculations:

  1. Mid-span Section of Frame: Calculate bending normal stress and shear stress, ensuring they do not exceed allowable values. For a 150-ton class trolley, the normal stress caused by mid-span bending is typically controlled below 120MPa (material Q345B).
  2. End Beam Connection Area: Calculate local compressive stress and weld strength. Especially under the dual trolley tandem lift condition, stress concentration at the connections is significant and requires reinforcement.
  3. Wheel Support Area: Calculate wheel pressure and contact stress, ensuring they do not exceed the allowable wheel pressure of the rail and wheels (QU70 rail allowable wheel pressure is approximately 120kN).

Finite Element Analysis:

Use software like SolidWorks or ANSYS to create a 3D model of the trolley, perform meshing, and set boundary conditions. Analyze stress distribution and deformation under typical working conditions, focusing on:

  • Torsional and bending composite stress on the frame under the dual trolley tandem lift condition.
  • Dynamic response caused by inertial forces during emergency braking.
  • The influence of lateral forces caused by wire rope sway.
    The analysis results must satisfy: maximum equivalent stress is less than material yield strength / safety factor (safety factor is typically 1.34); maximum deformation is less than 1/1000 of the span.

Fatigue Strength Check:

The trolley structure requires fatigue life assessment, especially at welds and stress concentration areas. Based on Miner’s linear cumulative damage theory, calculate the fatigue damage degree under different stress ranges; the total damage degree should be less than 1. For high-stress cycle areas, such as pulley support seats, measures like improving weld quality grade and optimizing transition fillets can be used to extend fatigue life.

Stability Analysis:

Compressed components of the trolley structure (e.g., box girder webs) require local stability checks. Calculate critical buckling stress based on plate and shell theory, ensuring working stress is below the critical value. If necessary, set longitudinal and transverse stiffeners to improve stability.

Manufacturing Process and Installation & Commissioning

The manufacturing quality of the double-girder gantry crane trolley directly affects its performance and safety reliability. This section provides detailed instructions on the manufacturing process, assembly procedure, and commissioning methods for the 150-ton class crane trolley, ensuring design intent is accurately translated into the actual product.

Material Selection and Pretreatment:

Main load-bearing structural components use Q345B low-alloy high-strength steel, which offers excellent comprehensive mechanical properties and good weldability. Upon arrival, steel plates undergo ultrasonic testing to ensure no internal defects. Before cutting, shot blasting pretreatment is performed to remove mill scale and achieve Sa2.5 cleanliness, followed by the application of a weldable shop primer.

Welding Process:

Main welds of the box girders use submerged arc automatic welding with K-type or V-type grooves, ensuring penetration rate not less than 80%. Fillet welds between stiffeners and webs use CO₂ gas shielded welding to reduce thermal deformation. All welds undergo visual inspection and non-destructive testing (ultrasonic or radiographic), with the testing proportion for main load-bearing welds not less than 20%. After welding, main structural components undergo overall stress relief annealing to eliminate welding residual stress.

Machining Process:

Key mating surfaces, such as wheel bearing seat mounting surfaces and reducer mounting surfaces, require milling, achieving a surface roughness of Ra3.2. Wheel axle holes are machined with CNC boring machines, with coaxiality error not exceeding 0.05mm. The mating surfaces of gear couplings are ground, ensuring contact area not less than 80%.

Assembly Procedure:

  1. Frame Assembly: Assemble box beams and end beams on a dedicated platform, using laser theodolites to detect straightness and flatness, with full-length error not exceeding 5mm.
  2. Mechanism Installation: First install the travel mechanism (wheel assemblies, reducers, motors), then install the hoisting mechanism (drum, pulley blocks, reducer), and finally install electrical equipment.
  3. Adjustment and Inspection: Check the relative position accuracy of various mechanisms, such as the deviation between the center plane of the drum and pulleys not exceeding 3mm, and wheel vertical skew not exceeding 1/1000.

Commissioning Methods:

  1. No-load Test: Operate each mechanism separately for 1 hour, check for abnormal vibration, noise, and heating; ensure brakes act flexibly and reliably.
  2. Static Load Test: Apply 125% of the rated load, suspend for 10 minutes, measure main girder deflection and structural stress, check for permanent deformation.
  3. Dynamic Load Test: Apply 110% of the rated load, perform combined hoisting and travel actions, test mechanism performance and electrical protection devices.

Anti-Corrosion Treatment:

After surface treatment reaches Sa2.5 level, apply epoxy zinc-rich primer (80μm) + epoxy mica iron intermediate coat (100μm) + polyurethane topcoat (60μm), with a total dry film thickness not less than 240μm. Friction surfaces (e.g., wheel treads, brake wheels) are not painted. All internal cavities of box girders are injected with anti-rust wax to prevent internal corrosion.

Acceptance Standards:

Acceptance is carried out according to GB/T14405-2011 “General Purpose Overhead Traveling Cranes” and GB/T14406-2011 “General Purpose Gantry Cranes”. Main indicators include:

  • Static Stiffness: When the trolley is at mid-span, the main girder deflection is not greater than 1/1000 of the span.
  • Dynamic Stiffness: Under rated load, the amplitude when the hoisting mechanism brakes does not exceed 1/2000 of the span.
  • Noise Level: Noise in the operator’s cabin is not greater than 85 dB(A).

Maintenance and Fault Handling

A scientific and reasonable maintenance system is key to ensuring the long-term, safe, and stable operation of the double-girder gantry crane trolley. Based on practical crane usage experience, this section provides a systematic maintenance plan and common fault handling methods to maximize equipment service life.

Daily Inspection System:

  1. Pre-shift Inspection: Before operation, check wire rope wear, brake operation, limit switch effectiveness, visible cracks in structural members, etc. Report any issues found immediately for repair.
  2. Weekly Inspection: Conduct detailed checks on pulley groove wear, coupling bolt tightness, wheel tread damage, lubricant level at lubrication points, etc. Clean dust from electrical components.
  3. Monthly Inspection: Measure key parameters such as brake clearance, wheel flange thickness, rail wear, etc. Record trend changes and predictively replace wearing parts.

Lubrication System Management:

Adopt a combination of centralized lubrication and manual lubrication:

  • Gear couplings, open gears, etc., use No. 00 lithium-based grease, replenished every 400 working hours.
  • Reducers use GB5903 industrial gear oil, replaced after the first 300 hours of operation, and subsequently every 5000 hours or annually.
  • Bearings use No. 2 lithium-based grease, replenished every 8 hours of operation.
  • Wire ropes use dedicated wire rope lubricant, applied weekly.

Key Component Life Management:

Establish a replacement cycle table for key components, for example:

  • Wire Rope: Generally recommended to be inspected every 6-12 months based on actual usage. Replace promptly if wear, broken wires, or corrosion are found.
  • Brake Linings: Regularly check the wear of brake linings. Replace when wear reaches the replacement standard. Simultaneously, adjust the tension of brake springs to ensure braking effectiveness.
  • Limit Switches: Regularly check the sensitivity and accuracy of limit switch operation. Adjust or replace promptly if errors or failure are detected.
  • Pulleys and Bearings: Regularly inspect the wear condition of pulley grooves. Replace promptly if excessive wear or damage is found. Also, regularly check the running condition of bearings. If abnormal noise or heating is found, inspect and replace the bearings promptly.

For the maintenance of the double-girder gantry crane trolley, in addition to the daily inspections and maintenance mentioned above, the equipment’s operation manual and relevant maintenance standards should also be followed to ensure long-term stable operation of the equipment. When a fault occurs, promptly identify the cause and take appropriate repair measures to avoid minor issues escalating and affecting the normal operation and service life of the equipment.

In the maintenance of the double-girder gantry crane trolley, special attention should also be paid to the life management of the following key components:

  • Controller: As the core component of the crane, controller maintenance is crucial. Regularly check the terminal connections, components, etc., of the controller for integrity. Address any looseness or damage promptly. Also, regularly clean dust from the controller to ensure its normal operation.
  • Remote Control: For double-girder gantry crane trolleys equipped with remote controls, remote control maintenance is equally important. Regularly check the battery, buttons, etc., of the remote control for integrity. Replace the battery if low or buttons if malfunctioning.
  • Safety Protection Devices: Safety protection devices are vital safeguards for the double-girder gantry crane trolley. Regularly check the sensitivity and reliability of safety protection devices. Adjust or replace promptly if abnormalities are found.

Based on the actual usage and equipment condition, and while following the equipment operation manual and relevant maintenance standards, the maintenance should also focus on personalized needs. Develop a reasonable maintenance plan to ensure the long-term stable operation of the equipment.

  Contact our crane specialists


Send us a message and we will get back to you as soon as possible.

    Send Your Needs